186. The authorization holder must draw up a daily report on the work and keep it on the activity site.
The daily report must contain all the elements applicable to the declared day including, in particular,
(1)  the completion authorization number;
(2)  a description, in chronological order, of the work carried out and the time required to carry out each step of the work;
(3)  the name of the enterprises that carry out the completion work;
(4)  a summary of the meteorological conditions;
(5)  the result of all the pressure and leak tests, including their duration and the initial and final test pressures;
(6)  the working condition of the blowout prevention system;
(7)  the well logs carried out;
(8)  the type of packers installed and the installation depths;
(9)  the technical details of the perforations, in particular, the number, type and intervals;
(10)  if applicable, the technical details of the completion by chemical stimulation, if applicable, in particular, the intervals, concentrations and volumes of acids and additives injected, the volume of flow-back water and the flows, and the injection pressures;
(11)  the composition, concentration and detailed assessment of all the products identified in the technical program that are stored or used on the activity site;
(12)  the number, interval, volume of fluid, injection rate and pressure and a summary of the results of each injectivity test;
(13)  the volume and composition of the gas used, released, incinerated or burnt at the flare;
(14)  the operational problems encountered and the corrective measures taken or planned;
(15)  the indication of any event that disrupted the planned progress of the work;
(16)  the indication of any temporary work interruption and the procedure followed to secure the well; and
(17)  any other information or document deemed necessary by the Minister.
O.C. 1252-2018, s. 186.
In force: 2018-09-20
186. The authorization holder must draw up a daily report on the work and keep it on the activity site.
The daily report must contain all the elements applicable to the declared day including, in particular,
(1)  the completion authorization number;
(2)  a description, in chronological order, of the work carried out and the time required to carry out each step of the work;
(3)  the name of the enterprises that carry out the completion work;
(4)  a summary of the meteorological conditions;
(5)  the result of all the pressure and leak tests, including their duration and the initial and final test pressures;
(6)  the working condition of the blowout prevention system;
(7)  the well logs carried out;
(8)  the type of packers installed and the installation depths;
(9)  the technical details of the perforations, in particular, the number, type and intervals;
(10)  if applicable, the technical details of the completion by chemical stimulation, if applicable, in particular, the intervals, concentrations and volumes of acids and additives injected, the volume of flow-back water and the flows, and the injection pressures;
(11)  the composition, concentration and detailed assessment of all the products identified in the technical program that are stored or used on the activity site;
(12)  the number, interval, volume of fluid, injection rate and pressure and a summary of the results of each injectivity test;
(13)  the volume and composition of the gas used, released, incinerated or burnt at the flare;
(14)  the operational problems encountered and the corrective measures taken or planned;
(15)  the indication of any event that disrupted the planned progress of the work;
(16)  the indication of any temporary work interruption and the procedure followed to secure the well; and
(17)  any other information or document deemed necessary by the Minister.
O.C. 1252-2018, s. 186.